As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing kerbing on the northern side of Port Road (from South Road to 423 Port Road, Croydon).

Key activities and timings

Between 7pm and 6am on Wednesday 12 July and Thursday 13 July 2017 (finishing 6am Friday 14 July 2017):

  • Removal of existing kerbing
  • Excavation for new kerbing

From 7am to 5pm Saturday 15 July 2017:

  • Installation of new kerbing

Equipment                                                                                                     

A vacuum truck, bobcat, excavator, trucks, compaction equipment, and light vehicles will be used to perform these works. Lighting towers will be in operation during night works.

Traffic management

  • Pedestrian access will be maintained.
  • Access to properties will be maintained.
  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Some noise can be expected, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au