UPCOMING NIGHT AND WEEKEND WORKS: CONTINUATION OF WORKS ON SOUTH ROAD BETWEEN TORRENS ROAD AND LAMONT STREET – 5/12/2016 – 16/12/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing service relocation and road preparation works on South Road between Torrens Road and Lamont Street, prior to switching traffic to the new north bound surface road between Torrens Road and Tait Street from 19 December 2016.

These works will be undertaken at various times from 7pm Monday 5 December to 7pm Friday 16 December 2016.

Key activities

  • Service relocations.
  • Excavation of pavement, backfill and reinstatement.
  • Removal of existing asphalt.
  • Asphalting works.

A vacuum truck, road saw, excavator, trucks, a small crane, grader, roller, profiler, asphalting equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions will apply on South Road and Torrens Road at various times, in the vicinity of the works.
  • Traffic signage will alert motorists to the changed traffic conditions.
  • Access to properties will be maintained.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au