UPCOMING NIGHT AND WEEKEND WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD, NEAR THE HAWKER/HURTLE STREET INTERSECTION – 22/07/16 TO 24/07/16

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing Telstra conduits in the northbound lanes on South Road, near the Hawker/Hurtle Street intersection.

To minimise disturbance to traffic, the works will be undertaken from 7pm Friday 22 July to 5pm Sunday 24 July 2016, weather permitting.

Key Activities

Trenching, laying of Telstra conduits, backfill and reinstatement works will be undertaken. An excavator, small crane, vacuum truck, tipper truck and light vehicles will be in operation. Lighting towers will also be operational during night works.

Traffic Management

  • Traffic will be reduced to one lane in each direction on South Road, between Harriet Street and Bedford Street
  • All traffic movements will continue to be provided at the South Road and Hawker Street intersection under traffic controller assistance
  • Speed restrictions will apply in the vicinity of works.
  • Pedestrian access will be provided under traffic controller assistance.
  • Bus services and bus stops will not be affected.
  • Signage will be in place to alert motorists and pedestrians to the changed traffic conditions.

Motorists can expect some traffic delays through the area while the works are in progress.

Some minor noise disturbance can also be expected while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au.