As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new driveways on the southern side of Torrens Road between Wright Street and South Road.
To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently between 7pm Friday 17 August and 6am Monday 20 August.
Key activities
A road saw, vacuum truck, excavator, trucks, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Traffic management
Works will be managed to minimise disturbance to local residents however some noise can be expected.