UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH TORRENS ROAD, CROYDON PARK – 27 – 30 JUNE 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new footpath around the north-eastern corner of the South Road intersection with Torrens Road.

To minimise disturbance to peak hour traffic and weather permitting, the works will take place between 7pm and 6am each day from Wednesday 27 to Friday 29 June and on Saturday 30 June between 7am and 5pm. 

Key activities 

  • Removal of existing footpath
  • Preparation works for the new footpath
  • Installation of new footpath

Excavators, road saws, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Driveway access to properties will be maintained.
  • Pedestrian access will be maintained.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au