UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET, RIDLEYTON – 20 – 21 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new footpaths around the South Road intersection with Hawker Street.

To minimise disturbance to peak hour traffic and weather permitting, the works will take place from 7pm Friday 20 July to 7pm Saturday 21 July.   

 Key activities

 Removal of existing footpaths

  • Installation of new footpaths and kerbing

Excavators, vacuum trucks, road saws, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

 Traffic management

  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access will be maintained.

Works will be managed to minimise disturbance to local residents however some noise can be expected.