UPCOMING EXCAVATION OF THE LOWERED MOTORWAY, SOUTH ROAD -UNDER PORT ROAD

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing excavation of the lowered motorway under Port Road.

The works will be undertaken each night between 7pm and 6am from:

  • Wednesday 30 August to Saturday 2 September 2017 (finishing 6am Saturday 2 September)
  • Monday 4 September to Friday 8 September 2017 (finishing 6am Friday 8 September)

Key activities

  • Excavation and wall trimming

Excavators, loaders and trucks will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

No additional pedestrian or traffic management will be required to carry out these works.

Works will be managed to minimise disturbance to local residents however some minor noise can be expected at times.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au