UPCOMING DAY WORKS FOR ELECTRICAL WORKS: ELIZABETH STREET, CROYDON – 4-8 SEPTEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing electrical conduits in the works area on Elizabeth Street between Cedar Avenue and William Street, Croydon.

The works will take place each day between 7am and 5pm from Monday 4 September to Friday 8 September 2017.

Traffic Management

  • No additional traffic management is required for these works.
  • Pedestrian access on Elizabeth Street will be maintained.

 Key activities

  • Excavation of trench
  • Installation of conduits

Excavators, vacuum trucks, road saws, trucks and light vehicles will be used to perform these works.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au