UPCOMING DAY AND NIGHT WORKS ON SOUTH ROAD FROM THE TORRENS ROAD INTERSECTION TO FORSTER STREET – January and February 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of works on South Road between the South Road intersection with Torrens Road and Forster Street.

To minimise disturbance to peak hour traffic, and weather permitting, the works will take place at various times from Friday 27 January to Monday 6 February 2017 (finishing 6am Monday 6 February 2017).

Locations and timing

· Installation of piles:

o South Road intersection with Torrens Road – between 7am and 7pm on Saturday 28 January and Sunday 29 January, and Saturday 4 February and Sunday 5 February 2017.

· Installation of stormwater infrastructure:

o South Road, south bound lanes, between Scotia Street and Bedford Street – intermittent day and night works from Friday 27 January to Monday 6 February 2017 (finishing 6am Monday 6 February 2017).

o South Road between Hythe Street and Monmouth Street – intermittent day and night works from Friday 27 January to Monday 6 February 2017 (finishing 6am Monday 6 February 2017).

· Installation of water main:

o South Road intersection with Hawker Street – between 7pm and 6am from Sunday 29 January to Monday 6 February 2017 (finishing 6am Monday 6 February 2017). No works will be undertaken on Thursday 2 February 2017.

o South Road between Hawker Street and Forster Street – between 7pm and 6am from Monday 30 January to Thursday 2 February 2017 (finishing 6am Thursday 2 February 2017).

Equipment

A vacuum truck, excavator, trucks, mobile cranes, compaction equipment and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic management

· Access to driveways will be maintained during these works, unless otherwise notified.

· Pedestrian access will be maintained.

· Lane and speed restrictions will apply in the vicinity of the works.

· Signage will alert motorists to the changed traffic conditions.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please visit contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au