The T2T Alliance will be installing a new gas main in Henry Street, between South Road and Elizabeth Street, Croydon.

To minimise disturbance to residents, the works will be undertaken each day between 7am and 5pm on Friday 15 July, Saturday 16 July, Monday 18 July and Tuesday 19 July 2016.  No works will occur on Sunday 17 July 2016.

Key activities

  • Excavation of a trench
  • Installation of the gas main
  • Backfill of the trench
  • Asphalting

Traffic Management

  • Henry Street, between South Road and Elizabeth Street, will be open to local traffic only during these works.
  • Access to properties will be maintained.
  • Traffic and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Please note: No gas outages are expected to occur as a result of these works.