TEMPORARY ROLLING CLOSURES OF ROBERT STREET, HENRY STREET AND CEDAR AVENUE, CROYDON- 30 APRIL – 1 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater works in the northbound lanes of South Road, between Euston Terrace and Cedar Avenue, Croydon.

To minimise the impact to peak hour traffic and weather permitting, these works will take place from 7pm Monday 30 April to 6am Tuesday 1 May.

To facilitate these works, there will be temporary rolling closures of Robert Street, Henry Street, and Cedar Avenue.

Key activities   

  • Investigation of stormwater pits and pipes.

Equipment

  • Hand tools and light vehicles will be used to perform these works.
  • Minimal noise can be expected during these works.

Traffic management

  • Temporary rolling closures as detailed above.
  • No more than one street will be closed at any time during these works.
  • Lane and speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions and available detours.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au