ROAD WORKS, TEMPORARY PARTIAL CLOSURE OF DAY TERRACE, CROYDON- 16 – 17 SEPTEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works at the junction of Day Terrace and Elizabeth Street (western side), Croydon.

To minimise disturbance, and weather permitting, these works will take place from
7pm Sunday 16 September to 4pm Monday 17 September.  

To facilitate these works, Day Terrace will be temporarily partially closed at Elizabeth Street, from
7pm Sunday 16 September to 4pm Monday 17 September.

Key activities   

  • Realignment of footpath ramp.

Equipment

An excavator, rock breaker (until 10pm only), hand tools, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Some noise and vibration can be expected during these works, however, the work will be managed to minimise disturbance to local residents and businesses as much as possible.Traffic management

  • Day Terrace will be temporarily partially closed at Elizabeth Street, from 7pm Sunday 16 September to 4pm Monday 17 September.
  • Access from Elizabeth Street in to Day Terrace will continue to be provided.
  • Motorists on Day Terrace wanting to access Elizabeth Street will be detoured via Thomas Street and Robert Street during this time.
  • Lane and speed restrictions will apply in the vicinity of the works
  • Signage will alert motorists to the changed traffic conditions

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au