As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of activities, including pavement reinstatement, asphalting, kerbing and footpath works and the installation of new stormwater infrastructure in the southbound lanes of South Road between Pym Street and Overland Road, Croydon Park.
Weather permitting, these works will take place as day and intermittent night works, from 7am Monday 26 March to 6am Monday 9 April, with the exception of the Easter period (6am Friday 30 March to 6am Tuesday 3 April) when no works will be undertaken.
To facilitate these works, Overland Road will be temporarily closed at South Road, from 6am Monday 26 March, following the re-opening of Pym Street, until 6am Monday 9 April.
Key activities
Equipment
Excavators, vacuum trucks, road saw, profilers, compaction equipment, paver, rock breaker, road saw, mobile crane, line-marking equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Some noise and vibration can be expected during these works, however, the work will be managed to minimise disturbance to local residents and businesses as much as possible.
Traffic management
Access to local businesses
Access to properties
Pedestrian access
For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au