ROAD WORKS, TEMPORARY CLOSURE OF MCINNES STREET, RIDLEYTON- 9 – 11 APRIL 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking electrical works across McInnes Street, near Orana, at 4 McInnes Street.

To minimise the impact to residents and businesses, and weather permitting, these works will take place each day between 7am and 6pm from Monday 9 April to Wednesday 11 April.

To facilitate these works, McInnes Street will be temporarily closed between South Road and 4 McInnes Street, between 7am and 6pm on Tuesday 10 April and Wednesday 11 April.

Key activities   

  • Excavation of trench
  • Installation of electrical conduits.
  • Backfill and reinstatement of the pavement.

Equipment

Excavators, vacuum trucks, road saw, compaction equipment, trucks and light vehicles will be used to perform these works.

Traffic management

  • McInnes Street will be temporarily closed between South Road and 4 McInnes Street, between 7am and 6pm on Tuesday 10 April and Wednesday 11 April.
  • Pedestrian access will continue to be provided on McInnes Street.
  • Access to some driveways may be temporarily impacted during these works.
  • Residents and business operators will be notified in advance of any works that will have a direct impact, such as temporary driveway restrictions.
  • Speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au

You can also contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au