As part of the Torrens Road to River Torrens Project, the T2T Alliance is continuing to undertake works on South Road between Pym Street and Overland Road.
To minimise disturbance to peak hour traffic, and weather permitting, night works will be undertaken each night, between 7pm and 6am from Sunday 4 February to Friday 9 February (finishing 6am Saturday 10 February).
Key activities
Excavators, compacting equipment, a backhoe, vacuum truck, agitator, road saws, piling rig, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Traffic arrangements
Works will be managed to minimise disturbance to local residents, however some noise and vibration can be expected.
For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au