NIGHT WORKS: PORT ROAD MEDIAN BETWEEN QUEEN STREET AND THE SA POWER NETWORKS SUBSTATION – 12 SEPTEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking works on the Port Road median (northern side) between Queen Street and the SA Power Networks sub-station in preparation for the opening of the median car park at the end of the week, weather permitting.

These works will be undertaken tonight, Tuesday 12 September 2017 from 7pm to 12midnight. These works have been brought forward to avoid forecast wet weather conditions later in the week.

Key activities

  • Grading the Port Road median (northern side) to make the area level, adjacent to the footpath and new median car park.

A grader, truck and light vehicles will be used to perform these works. Lighting towers will  also be in operation during night works.

Traffic Management

  • A single lane closure on Port Road between King Street and South Road for city bound traffic and speed restrictions will be in place during these works.

Works will be managed to minimise disturbance to local residents however some minor noise can be expected at times.

For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au