As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement works at the South Road junctions with Paget Street and Hythe Street, Ridleyton.
To minimise disturbance to peak hour traffic, and weather permitting, the works will be undertaken from 7pm Friday 9 February to 6am Monday 12 February. Testing of the pavement will also be undertaken intermittently from 7pm Monday 12 February to 6am Tuesday 13 February.
Key activities
Profilers, compaction equipment, paver, rock breaker, road saw, mobile crane, line-marking equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.
Some noise and vibration can be expected during these works, however, the work will be managed to minimise disturbance to local residents and businesses as much as possible.
Traffic management
For further information about these works please contact us on: 1300 794 899, or email at: enquiries@t2talliance.com.au