UPDATE: NIGHT AND WEEKEND WORKS: KERBING AND ASPHALTING WORKS AT THE QUEEN STREET U-TURN FACILITY ON PORT ROAD – 05/08/2016 TO 10/08/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing kerbing and asphalting the U-turn facility on Port Road, near Queen Street.

These works have taken longer than expected due to poor weather conditions and additional time is required to complete them. The remaining works will be completed from:

  • 7pm Friday 5 August to 5pm Saturday 6 August 2016.
  • 7pm Tuesday 9 August to 6am Wednesday 10 August 2016.
Key activities
  • Barrier removal and minor excavation works.
  • Install kerbing.
  • Profiling and asphalting.
Traffic Management
  • Traffic and speed restrictions on Port Road and Queen Street will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.

Some minor noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

For further information about these works please contact us on: 1300 794 899, or email: enquiries@t2talliance.com.au.