CONTINUATION OF WORKS FOR THE OUTER HARBOR RAIL OVERPASS- 7/11/2016 – 11/11/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing works for the Outer Harbor rail overpass, along the rail corridor between the Elizabeth Street / Queen Street and Coglin Street rail crossings.

Crews will be working across various sites to complete the works.

Locations and key activities:

Between South Road and the Coglin Street rail crossing  

  • Night works will take place between 7pm and 6am from Monday 7 November to Saturday 11 November 2016
  • Installation of retaining walls within the rail corridor

A 350 Tonne road crane, mobile crane, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Some noise disturbance can be expected at times while these works are completed, however the work will be managed to minimise disturbance to local residents as much as possible.

Between South Road and the Elizabeth Street / Queen Street rail crossing

  • Day works will take place intermittently between 7am and 5pm from Monday 7 November to Saturday 11 November
  • Installation of Gabion walls

Traffic Management

  • Euston Terrace between Queen Street and South Road will be open to local traffic only during these works.
  • Access to property driveways will be maintained.
  • We will contact property occupiers in advance, should any temporary impacts to property access occur during the works.

For further information about these works, including the latest traffic arrangements, please visit www.t2talliance.com.au