CONTINUATION OF NIGHT WORKS: SERVICE RELOCATIONS ON SOUTH ROAD, BETWEEN HAWKER STREET AND MCINNES STREET – 30/10/2016 – 05/11/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to relocate services on the eastern side of South Road, between Hawker Street and McInnes Street.

Crews will be working across various sites within the area to complete the works.

To minimise disturbance to peak hour traffic, and weather permitting, the works will take place between 7pm and 6am from Sunday 30 October to Saturday 5 November 2016 (finishing 6am Saturday 5 November 2016).

Locations and key activities:

  • South Road intersection with Hawker Street
    • Installation of a new water main.
  • South Road between Hawker Street and Paget Street
    • Completion of service utility pits.
    • Intermittent works to reinstate footpaths.
  • South Road between Paget Street and McInnes Street
    • Installation of a new water main.
    • Completion of service utility pits.
    • Temporary reinstatement of the trench.

Equipment:

  • A vacuum truck, rock breaker, road saw, mobile crane, excavator, compaction equipment, trucks and light vehicles will be used to perform these works.
  • Lighting towers will also be in operation during night works.

Traffic Management

  • Lane and speed restrictions on South Road will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access on South Road will be maintained with the assistance of a traffic controller.

Works will be managed to minimise disturbance to local residents however some noise can be expected.