CONTINUATION OF NIGHT WORKS: INSTALLATION OF A WATER MAIN ON SOUTH ROAD AT THE HAWKER STREET INTERSECTION – 1/12/2016 – 2/12/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing the installation of a new water main on the eastern side of the South Road. Crews are currently working across various sites between McInnes Street and Torrens Road.

Works will be undertaken to install the new water main on South Road at the Hawker Street intersection between 7pm Thursday 1 December 2016 and 6am Friday 2 December 2016.

Key activities

  • Identification of services, saw cutting of the road pavement.
  • Excavation of a trench, pipe laying and reinstatement.

A vacuum truck, road saw, mobile crane, excavator, compaction equipment, trucks and light vehicles will be used to perform these works. Lighting towers will also be in operation during night works.

Traffic Management

  • Traffic will be reduced to one lane in each direction on South Road and Hawker Street at the intersection.
  • Traffic signals will turned off during the works and movements controlled by traffic controllers.
  • All turning movements will be allowed at the intersection.
  • Speed restrictions will apply in the vicinity of the works.
  • Signage will alert motorists to the changed traffic conditions.
  • Pedestrian access on South Road will be maintained.

Works will be managed to minimise disturbance to local residents however some noise can be expected.

For further information about these works, including the latest traffic arrangements, please contact us on: 1300 794 899, or email: enquiries@t2talliance.com.au