Interactive Construction Zone Map

The Torrens Road to River Torrens Project has been split into 12 work zones. The map below shows each work zone and the geographical locations within each zone. Construction activities will be described as taking place in each work zone. To view the current works, road closures and notifications relevant to each zone please click on the map below.

Zone 1 Zone 2 Zone 3 Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 Zone 9 Zone 10 Zone 10A Zone 11 Zone 12 Zone 12A map_legends

Zone 1 – Torrens River to Adam Street

Current notifications and works for zone 1:

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

Linear Park Trail is open to pedestrians and cyclists

 

Zone 3 – Hindmarsh Avenue to Grange Road

Current notifications and works for zone 3:

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

UPCOMING DAY WORKS AT THE JERVOIS AVENUE PARK, WEST HINDMARSH – STARTING FROM 23 OCTOBER 2018

Bus Stops

Bus stop 9 and 11 (eastern side) of South Road are permanently closed, please use Bus stop 10.

Bus stop 9 on the western side is permanently closed, please use Bus stop 10 near Gawler Avenue.

Zone 5 – Grange Road to Port Road

Current notifications and works for zone 5:

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

Permanent Road Closures:

  • Bond Street (at South Road)

Zone 7 – Port Road to Robert Street

Current notifications and works for zone 7:

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

TEMPORARY CLOSURE OF FOOTPATH ON THE EASTERN SIDE OF SOUTH ROAD BETWEEN FORESTER STREET AND MCINNES STREET, RIDLEYTON- FROM FRIDAY 9 NOVEMBER FOR APPROXIMATELY FOUR WEEKS

Temporary Road Closure (dates subject to change):

  • McInnes Street (at South Road) – Pedestrian access available

Temporary footpath closure: 

  • Temporary closure between Forster Street and McInnes Street from 9 November for approximately four weeks

Permanent Road Closures:

  • Princes Street (at South Road)
  • Euston Terrace (at South Road)

Pedestrian and cyclist access:

West Street, Coglin Street and Queen Street

Activation of pedestrian crossings at Queen Street, Coglin Street and West Street will not be undertaken until early 2019. The delay in activation is the result of signalling design, and this remains outside the control of the T2T Alliance. Until the level crossing at West Street can be activated, it must remain closed for safety reasons. Further notice about the timing of level crossings activation will be provided.

Pedestrian and cyclists are able to cross at the level crossings on the eastern side of the level crossings at Queen Street and Coglin Street.

 

 

Zone 8 – Outer Harbor Rail Bridge

Current notifications and works for zone 8:

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

Pedestrian and cyclist access:

West Street, Coglin Street and Queen Street

Activation of pedestrian crossings at Queen Street, Coglin Street and West Street is not anticipated to be undertaken until April 2019. The delay in activation is the result of signalling design, and this remains outside the control of the T2T Alliance. Until the level crossing at West Street can be activated, it must remain closed for safety reasons. Further notice about the timing of level crossings activation will be provided.

Pedestrian and cyclists are able to cross at the level crossings on the eastern side of the level crossings at Queen Street and Coglin Street.

Outer Harbor Greenway now open between Day Terrace and West Street

850 metres of new Outer Harbor Greenway path is now open including a bridge over South Road as part of the T2T project. The shared use path links Day Terrace (Croydon) to West Street (Brompton) with on road connections to the new underpass of Park Terrace and the quiet street routes to Port Adelaide and beyond.  You can explore the bicycle facilities around Adelaide at www.cycleinstead.com.au

Zone 9 – Robert Street to Cedar Avenue

Current notifications and works for zone 9:

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

Permanent Road Closures:

  • William Street (at South Road)

 

Zone 10 – Cedar Avenue to Torrens Road

Current notifications and works for zone 10:

ROAD WORKS, TEMPORARY CLOSURE OF LAMONT STREET- 20 – 22 NOVEMBER 2018

 

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

Permanent Road Closures:

  • Hurtle Street (at South Road) (Cyclist and pedestrian access provided)
  • Scotia Street (at South Road)
  • Dartmouth Street (at South Road) closed to left turn in (left turn out only) as per the final design

Zone 12A – Sunbeam Road to Royce Avenue

Current notifications for zone 12A:

ROAD WORKS, TEMPORARY CLOSURE OF LAMONT STREET- 20 – 22 NOVEMBER 2018

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN ADAM STREET, HINDMARSH AND PYM STREET, CROYDON PARK – FROM MONDAY 12 NOVEMBER FOR APPROXIMATELY THREE WEEKS

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH PYM STREET, CROYDON PARK- 6 – 9 NOVEMBER 2018

Permanent Road Closures:

  • Overland Road (western side) closed at South Road as per the final design configuration
  • Auburn Crescent closed at South Road as per the final design configuration.