UPCOMING DAY WORKS AT THE JERVOIS AVENUE PARK, WEST HINDMARSH – STARTING FROM 23 OCTOBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be clearing the land on Jervois Avenue in preparation for the community park. To minimise disturbance to the local community, these works will be undertaken intermittently each day between 7am and 6pm from Tuesday 23 October for approximately two weeks. Removal […]

NIGHT AND WEEKEND WORKS – TEMPORARY CLOSURE OF SOUTH ROAD SOUTHBOUND- FRIDAY 12 OCTOBER – MONDAY 15 OCTOBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works on the southbound lanes of South Road between Hotchkiss Crescent, Croydon Park and West Thebarton Road, Thebarton. To facilitate these works the southbound lanes of South Road will be temporarily closed to traffic between Regency Road, Croydon […]

NIGHT AND WEEKEND WORKS – TEMPORARY CLOSURE OF SOUTH ROAD NORTHBOUND- 7PM FRIDAY 5 OCTOBER- 6AM MONDAY 8 OCTOBER 2018

As part f the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works on the northbound lanes of South Road between Royce Avenue, Croydon Park and Ashwin Parade, Torrensville. To facilitate these works the northbound lanes of South Road will be temporarily closed to traffic between Regency Road, Croydon Park […]

TEMPORARY CLOSURE OF FOOTPATH ON THE EASTERN SIDE OF SOUTH ROAD BETWEEN MCINNES STREET AND RIDLEY STREET HINDMARSH- FROM 26 SEPTEMBER FOR APPROX OF FOUR WEEKS

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works on the underside of the Outer Harbor rail bridge. To safely facilitate these works: The footpath on the eastern side of South Road between McInnes Street and Ridley Street will be temporarily closed from 7pm Wednesday 26 […]

REMINDER – TEMPORARY CLOSURE OF LINEAR PARK TRAIL, BETWEEN MCDONNELL AVENUE AND SOUTH ROAD, WEST HINDMARSH- WILL REMAIN CLOSED UNTIL MID TO LATE NOVEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance is continuing works to widen Taylor Bridge until late 2018. To facilitate these works: The Linear Park Trail will remain closed between McDonnell Avenue and South Road until mid to late November 2018. Signage has been erected in strategic locations to direct […]

RESCHEDULED WORKS REQUIRING TEMPORARY CLOSURE OF COGLIN STREET RAIL CROSSING, BROMPTON- 7pm Wednesday 26 September and 6am Friday 28 September

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works on Coglin Street, Brompton, near the rail crossing. To minimise disturbance, and weather permitting, these works will be undertaken between 7pm Wednesday 26 September and 6am Friday 28 September. To safely undertake these works, the rail crossing […]

UPDATE: ROAD WORKS, TEMPORARY PARTIAL CLOSURE OF HENRY STREET, CROYDON- 25 SEPTEMBER 2018

  As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works at the junction of Henry Street and South Road, Croydon. Due to technical difficulties, these works will now take place from 6am to 7pm Tuesday 25 September. To facilitate these works, Henry Street will be temporarily […]

COMMUNITY CELEBRATION – SUNDAY 23 SEPTEMBER 2018 11AM – 3PM

JOIN US AT THE T2T COMMUNITY CELEBRATION IN THE LOWERED MOTORWAY SUNDAY 23 SEPTEMBER 2018 FROM 11AM TO 3PM The celebration will take place in the lowered motorway, under the Port Road bridge, Hindmarsh. What’s happening: A free sausage sizzle Refreshments available for purchase Free children’s activities Community groups and business displays Construction equipment on […]

T2T Community Celebration 23 September from 11am – 3pm under Port Road Bridge

The T2T Community celebration is shaping up to be a great day of food, entertainment and family fun. The celebration will include the West Torrens Rotary Club cooking a free sausage sizzle along with food trucks and stalls selling food and drinks including: AJ’s Food Truck Café 2U Gelista Gelati Mumbai Magic Indian Takeaway Rheinland […]

ROAD WORKS, TEMPORARY PARTIAL CLOSURE OF HENRY STREET, CROYDON – 20/9/18

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works at the junction of Henry Street and South Road, Croydon. To minimise disturbance, and weather permitting, these works will take place from 6am to 7pm Thursday 20 September. To facilitate these works, Henry Street will be temporarily […]

RE-OPENING OF THE LINEAR PARK TRAIL UNDER SOUTH ROAD, NEAR TAYLOR BRIDGE

Linear Park trail under South Road is scheduled to re-open by November 2018.  Piling works for the shared use path under South Road, which forms part of the Linear Park Trail have recently commenced after these activities were delayed due to rainy weather and potential flooding issues. We apologise for any inconvenience the delayed opening […]

NIGHT AND WEEKEND WORKS – TEMPORARY CLOSURES SOUTH ROAD AND PORT ROAD – 6 – 9 SEPTEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking: Major pavement works at the South Road intersection with Port Road, and on Port Road between Queen Street and Coglin Street. Gantry installation in southbound lanes of South Road between Hawker Street and Port Road. To minimise disruption to […]

UPCOMING WEEKEND WORKS ON SOUTH ROAD BETWEEN HOTCHKISS CRESCENT AND OVERLAND ROAD, CROYDON PARK – 8 – 9 SEPTEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works and installing a centre median along South Road between Hotchkiss Crescent and north of Overland Road, Croydon Park. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently between 7am and […]

Construction Newsletter September 2018

The 9th edition of Construction Newsletter is now available. To view the Construction Newsletter please click here. To view a map showing entry and exit points into the lowered motorway, once it is operational (a date yet to be advised) click here.

ROAD WORKS, TEMPORARY CLOSURE OF PYM STREET – 2 – 10 SEPTEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of activities at the South Road intersection with Pym Street, requiring a temporary closure of Pym Street. To safely undertake these works, Pym Street will be temporarily closed to the east of South Road from 7pm, Sunday, […]

UPCOMING NIGHT AND WEEKEND WORKS ON GRANGE ROAD/MANTON STREET BETWEEN BERTIE STREET, WEST HINDMARSH AND BACON STREET, HINDMARSH – 31 AUGUST – 3 SEPTEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking pavement works and installing a centre median along Grange Road/Manton Street between Bertie Street and Bacon Street. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently between 7pm Friday 31 August and […]

UPCOMING NIGHT WORKS ON PORT ROAD BETWEEN SOUTH ROAD AND QUEEN STREET – 29 AUGUST – 6 SEPTEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking finishing works on Port Road between South Road and Queen Street. To minimise disturbance to peak hour traffic, and weather permitting, the works will be undertaken intermittently each night between 7pm and 6am from: Wednesday 29 August to Friday […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET, RIDLEYTON – 8 -9 AUGUST 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking work at South Road intersection with Hawker Street. To minimise disturbance to peak hour traffic and weather permitting, the works will take place between 7pm Wednesday 8 August and 6 am Thursday 9 August.    Key activities  Replacement of […]

TEMPORARY CLOSURE OF FOOTPATH ON THE WESTERN SIDE OF SOUTH ROAD BETWEEN HARRIET STREET AND BEDFORD STREET, CROYDON – 5 -11 AUGUST 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new footpath on the western side of South Road between Harriet Street and Bedford Street. To safely facilitate these works: The footpath on the western side of South Road between Harriet Street and Bedford Street will be temporarily […]

TEMPORARY CLOSURE OF HAWKER STREET, RIDLEYTON – 3 – 6 AUGUST 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of activities at the South Road intersection with Hawker Street, Ridleyton. To minimise the impact to peak hour traffic, and weather permitting, these works will take place from 7pm Friday 3 August to 6am Monday 6 August. […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET, RIDLEYTON – 1 – 3 AUGUST 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of activities at the South Road intersection with Hawker Street. To minimise disturbance to peak hour traffic and weather permitting, the works will take place between 7pm and 6am on Wednesday 1 August and Thursday 2 August […]

UPCOMING NIGHT WORKS ON PORT ROAD BETWEEN SOUTH ROAD AND QUEEN STREET – 1 – 6 AUGUST 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be repairing service pits for the Common Services Trench in various locations within the Port Road median between South Road and Queen Street. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken each night between […]

CONSTRUCTION OF THE LOWERED MOTORWAY, SOUTH ROAD – 30 JULY – 3 AUGUST 2018

the lowered motorway, between Lamont Street, Croydon Park and Susan Street, Hindmarsh. From Monday 30 July to Friday 3 August asphalting of the lowered motorway will occur between Torrens Road and Overland Road from 6am each day until 1am each night, weather permitting. Key activities Laying of new pavement and asphalting. Excavators, backhoes, loaders, asphalt […]

UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH PORT ROAD, AND ON PORT ROAD BETWEEN COGLIN STREET, HINDMARSH, AND QUEEN STREET, CROYDON – 27 – 30 JULY

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking various activities at the South Road intersection with Port Road, and on Port Road between Queen Street and Coglin Street. To minimise disturbance to peak hour traffic, the works will be undertaken from 7pm Friday 27 July to 6am […]

ROAD WORKS, TEMPORARY PARTIAL CLOSURE OF SUSAN STREET, HINDMARSH – 30 JULY – 3 AUGUST

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new footpaths and kerbing at the South Road junction with Susan Street, Hindmarsh. To minimise the impact to peak hour traffic and weather permitting, these works will take place from       5am Monday 30 July to 7pm Friday 3 August. […]

TEMPORARY CLOSURE OF THE CEDAR AVENUE PEDESTRIAN BRIDGE ACROSS SOUTH ROAD – 25 – 27 JULY

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking bridge works at the Cedar Avenue pedestrian bridge across South Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken from 7pm Wednesday 25 July to and 6am Friday 27 July. Key activities                                                                                                               […]

UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET, RIDLEYTON – 20 – 21 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new footpaths around the South Road intersection with Hawker Street. To minimise disturbance to peak hour traffic and weather permitting, the works will take place from 7pm Friday 20 July to 7pm Saturday 21 July.     Key activities  Removal […]

UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH TORRENS ROAD – 19 -23 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new traffic islands at the South Road intersection with Torrens Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently during the following times: 7pm Thursday 19 July to 6am Friday 20 […]

UPCOMING NIGHT WORKS ON TORRENS ROAD NEAR DAYS ROAD, RENOWN PARK / WEST CROYDON – 18 – 19 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking signalling works in the centre median of Torrens Road, just east of the intersection with Days Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently each night between 7pm and 6am […]

UPCOMING NIGHT WORKS ON SOUTH ROAD NEAR PRINCES STREET, CROYDON – 18 – 19 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking lighting works in the northbound lanes of South Road, near Princes Street, Croydon. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently each night between 7pm and 6am on Wednesday 18 July […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH TORRENS ROAD, CROYDON – 11 – 13 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking lighting and signal pit works in the northbound lanes of South Road north and south of the intersection with Torrens Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken from 7pm Wednesday […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET, RIDLEYTON – 11 – 16 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new footpaths around the South Road intersection with Hawker Street. To minimise disturbance to peak hour traffic and weather permitting, the works will take place between 7pm and 6am, from Wednesday 11 July to Monday 16 July (finishing 6am […]

TEMPORARY CLOSURE OF THE CEDAR AVENUE PEDESTRIAN BRIDGE ACROSS SOUTH ROAD – 16 – 20 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking bridge works at the Cedar Avenue pedestrian bridge across South Road. These works will be undertaken each day between 7am and 5pm from Monday 16 July to Friday 20 July, weather permitting.   Key activities                                                                                                Installation of expansion joints. […]

UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD BETWEEN TORRENS ROAD, CROYDON AND HAWKER STREET, RIDLEYTON- 6 – 9 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be replacing sewer manhole lids in the southbound lanes of South Road between Torrens Road, Croydon and Hawker Street, Ridleyton. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken from 7pm Friday 6 July to […]

UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD BETWEEN BEDFORD STREET, CROYDON AND BISHOP STREET, RENOWN PARK – 6 JULY – 9 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new footpaths and kerbing in both directions along South Road between Bedford Street and Bishop Street. To minimise disturbance to peak hour traffic, and weather permitting, the works will be undertaken from 7pm Friday 6 July to […]

UPCOMING NIGHT AND WEEKEND WORKS ON PORT ROAD, HINDMARSH- 29 JUNE – 2 JULY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking sections of pavement works in the westbound lanes of Port Road and in the Port Road median crossing at Coglin Street. To minimise disturbance to peak hour traffic, the works will be undertaken from 7pm Friday 29 June to […]

RAIL WORKS UPDATE – JUNE 2018

Since the last update in April, the following works have been undertaken: Tamping of the rail to efficiently pack (tamp) the track ballast under the railway tracks to achieve the desired alignment A pedestrian bridge, forming part of the Outer Harbor Greenway, at Chief Street, on the northern side of the Outer Harbor rail bridge […]

CONSTRUCTION OF THE LOWERED MOTORWAY, SOUTH ROAD – JUNE – END OF SEPTEMBER 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing construction of the lowered motorway, between Lamont Street, Croydon Park and Susan Street, Hindmarsh. Key activities will be occurring concurrently within the motorway with works progressing from south to north.Works will be undertaken during the day from 4am and intermittently […]

TEMPORARY CLOSURE OF LINEAR PARK TRAIL, BETWEEN MCDONNELL AVENUE AND SOUTH ROAD, WEST HINDMARSH

The Linear Park Trail will be temporarily closed between McDonnell Avenue and South Road from 7pm Monday, 11 June for approximately three months.  The temporary structure which has been in place under South Road and forms part of the Linear Park Trail must be removed, as the potential for high rainfall events during the winter […]

TEMPORARY CLOSURE OF HAWKER STREET, RIDLEYTON- 30 MAY – 31 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater works in the southbound lanes of South Road, through the intersection with Hawker Street, Ridleyton. To minimise the impact to peak hour traffic and weather permitting, these works will take place from 7pm Wednesday 30 May to 6am Thursday […]

UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD, WEST HINDMARSH- 25 – 28 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking pavement works on the northbound lanes of South Road, from just south of Grange Road to Port Road. To minimise disturbance to peak hour traffic, the works will be undertaken from 7pm, Friday, 25 May to 6am, Monday, 28 […]

UPCOMING NIGHT WORKS REQUIRING TEMPORARY PARTIAL CLOSURE OF COGLIN STREET RAIL CROSSING, BROMPTON- 25 – 26 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking pavement works on the shared use path that runs adjacent to the rail corridor between South Road and Coglin Street, Brompton. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken from 7pm Friday 25 […]

UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD NEAR THE BRICKWORKS MARKET PLACE, TORRENSVILLE  – 25 – 28 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new stormwater infrastructure in the southbound lanes of South Road near the Brickworks Market Place, Torrensville. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken from 7pm Friday 25 May to 6am Monday […]

TEMPORARY CLOSURE OF TORRENS ROAD WEST OF THE SOUTH ROAD INTERSECTION – 18 – 21 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement and asphalt works on Torrens Road between the west side of the intersection with South Road to the Days Road / Lamont Street intersection. To minimise disturbance to peak hour traffic, the works will be undertaken from […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH PORT ROAD – 20-23 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new stormwater infrastructure at the South Road intersection with Port Road (southeast corner) and in the southbound lanes of South Road between Port Road and Orsmond Street. To minimise disturbance to peak hour traffic, and weather permitting, […]

FINAL TRAFFIC ARRANGEMENTS ON SOUTH ROAD SOUTHBOUND FROM HOTCHKISS CRESCENT TO ADAM STREET

As part of the Torrens Road to River Torrens Project, the T2T Alliance has now moved all southbound traffic on South Road in its final road alignment between Hotchkiss Crescent, Croydon Park and Adam Street, Hindmarsh. As per the final design, no parking on South Road is permitted. Yellow line marking, in addition to signage […]

UPCOMING WORKS, TEMPORARY ROAD CLOSURES, TORRENS ROAD – 7PM FRIDAY 11 MAY TO 6AM MONDAY 14 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement and asphalt works on Torrens Road between the east side of the intersection with South Road to Wright Street. To minimise disturbance to peak hour traffic, the works will be undertaken from 7pm, Friday, 11 May to […]

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN TORRENS AVENUE AND HINDMARSH AVENUE, WEST HINDMARSH – 1 – 4 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking common Services trench works on the western side of South Road between Torrens Avenue and Hindmarsh Avenue. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently between 7pm and 6am from Tuesday 1 May to […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET, CROYDON- 4 – 7 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new stormwater infrastructure in the northbound lanes of South Road, through the intersection with Hawker Street. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken from 7pm Friday 4 May to 6am […]

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN TAIT STREET AND TORRENS ROAD, RENOWN PARK – 2 – 5 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new footpath on the eastern side of South Road between Tait Street and Torrens Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently between 7pm and 6am from Wednesday 2 May to Friday […]

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN BENNET STREET AND ASHLEY STREET, TORRENSVILLE- 3 – 4 & 4 -7 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking directional boring and installing communication conduits on South Road between Bennet Street and Ashley Street, Torrensville. To minimise disturbance to peak hour traffic, and weather permitting, the works will be undertaken at the following times: ·         From 7pm Thursday 3 May to […]

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN PYM STREET AND OVERLAND ROAD, CROYDON PARK – 30 APRIL – 1 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing a new footpath on the eastern side of South Road between Pym Street and Overland Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken intermittently between 7pm and 6am on Monday 30 […]

ROAD WORKS, TEMPORARY CLOSURE OF OVERLAND ROAD, CROYDON PARK- 1 – 2 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater works in the southbound lanes of South Road, near Overland Road, Croydon Park. To minimise the impact to peak hour traffic and weather permitting, these works will take place from 7pm Tuesday 1 May to 4am Wednesday 2 […]

TEMPORARY CLOSURE OF HAWKER STREET, RIDLEYTON- 1 – 2 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater works in the southbound lanes of South Road, through the intersection with Hawker Street, Ridleyton. To minimise the impact to peak hour traffic and weather permitting, these works will take place from 7pm Tuesday 1 May to 6am […]

TEMPORARY ROLLING CLOSURES OF HARRIET, BEDFORD AND DARTMOUTH STREETS, CROYDON- 2 – 3 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater works in the northbound lanes of South Road, between Harriet Street and Torrens Road, Croydon. To minimise the impact to peak hour traffic and weather permitting, these works will take place from 7pm Wednesday 2 May to 6am […]

TEMPORARY ROLLING CLOSURES OF ROBERT STREET, HENRY STREET AND CEDAR AVENUE, CROYDON- 30 APRIL – 1 MAY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater works in the northbound lanes of South Road, between Euston Terrace and Cedar Avenue, Croydon. To minimise the impact to peak hour traffic and weather permitting, these works will take place from 7pm Monday 30 April to 6am […]

TEMPORARY ROLLING CLOSURES OF PAGET, HYTHE, MONMOUTH AND FORSTER STREETS, RIDLEYTON- 29 -30 APRIL 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking stormwater works in the southbound lanes of South Road, between Paget Street and Forster Street, Ridleyton. To minimise the impact to peak hour traffic and weather permitting, these works will take place from 7pm Sunday 29 April to 6am […]

UPCOMING WORKS ON SOUTH ROAD BETWEEN ASHWIN PARADE / WEST THEBARTON ROAD AND SUSAN STREET, WITH TEMPORARY LOCAL ROAD CLOSURES – 13 – 30 APRIL 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement and asphalt works on South Road between Ashwin Parade / West Thebarton Road and Susan Street. To minimise disturbance to peak hour traffic, the works will be undertaken during school holidays from 7pm Friday 13 April to […]

T2T – COMMUNITY INFORMATION DROP IN DAY – SATURDAY 14 APRIL 11AM TO 2PM

ROAD WORKS, TEMPORARY CLOSURE OF OVERLAND ROAD, CROYDON PARK – 26 MARCH – 9 APRIL 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of activities, including pavement reinstatement, asphalting, kerbing and footpath works and the installation of new stormwater infrastructure in the southbound lanes of South Road between Pym Street and Overland Road, Croydon Park. Weather permitting, these works will […]

TEMPORARY CLOSURE OF FOOTPATH ON THE EASTERN SIDE OF SOUTH ROAD BETWEEN ADAM STREET AND 31 SOUTH ROAD, WEST HINDMARSH – 7 MARCH TO LATE MARCH 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new footpaths and kerbing on the eastern side of South Road between Adam Street and 31 South Road (Hindmarsh Plumbing). To safely facilitate these works: The footpath on the eastern side of South Road between Adam Street […]

UPCOMING DAY WORKS IN THE FLANDERS STREET COMPOUND, CROYDON PARK – 6-16 MARCH 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking excavation works in the Flanders Street compound from 7am Tuesday 6 March for approximately 10 days. During these works trucks will be entering and exiting the site via Torrens Road, Lamont Street and Flanders Street. For further information about […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH TORRENS ROAD, AND ON TORRENS ROAD BETWEEN WRIGHT STREET AND ELLEN STREET – 5-9 MARCH 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a new water main at the South Road intersection with Torrens Road, and on Torrens Road between Wright Street and Ellen Street. To minimise disturbance to peak hour traffic, and weather permitting, the works will be undertaken […]

TREE PRUNING ON CHARRON ROAD – 1 MARCH 2018

As part of the Torrens Road to River Torrens Project, we will be undertaking some tree pruning works on Charron Road, Croydon Park. The tree pruning is required to enable Adelaide Metro buses to safely travel along Charron Road as part of the bus detour route for the closure of Pym Street, as advised in […]

TEMPORARY CLOSURE OF FOOTPATH ON THE EASTERN SIDE OF ELIZABETH STREET BETWEEN WILLIAM STREET AND CEDAR AVENUE, CROYDON – 1 MARCH FOR 4 WEEKS

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking electrical works on Elizabeth Street between William Street and Cedar Avenue. To safely facilitate these works: The footpath on the eastern side of Elizabeth Street between William Street and Cedar Avenue will be temporarily closed from Thursday 1 March […]

TEMPORARY CLOSURE OF FOOTPATH ON THE EASTERN SIDE OF SOUTH ROAD BETWEEN BISHOP STREET AND OVERLAND ROAD, CROYDON PARK – LATE MARCH 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing a range of activities on the eastern side of South Road between Torrens Road and Pym Street. To safely facilitate these works: The footpath on the eastern side of South Road between Bishop Street and Overland Road will be […]

UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD BETWEEN MONMOUTH STREET AND FORSTER STREET, RIDLEYTON, WITH TEMPORARY CLOSURE OF SOUTH ROAD – 2-5 FEBRUARY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement and asphalt works in the southbound lanes of South Road between Monmouth Street and Forster Street, Ridleyton. To minimise disturbance to peak hour traffic, the works will be undertaken from 7pm Friday 2 February to 6am Monday […]

UPDATE: TEMPORARY CLOSURE OF FOOTPATH ON THE WESTERN SIDE OF SOUTH ROAD BETWEEN PYM STREET AND ROYCE AVENUE, CROYDON PARK – UNTIL 3 APRIL 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new kerbing and footpaths on the western side of South Road between Pym Street and Royce Avenue. To safely facilitate these works: The footpath on the western side of South Road between Pym Street and Royce Avenue […]

UPCOMING NIGHT WORKS ON SOUTH ROAD AND PORT ROAD INTERSECTION- 31 JANUARY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to undertake traffic signalling works at the intersection of South Road and Port Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be undertaken between 7pm and 6am on Wednesday 31 January (finishing 6am […]

RAIL WORKS UPDATE: NIGHT WORKS AT CROYDON STATION – 30 JANUARY – 3 FEBRUARY 2018

As part of the Torrens Road to River Torrens Project a range of finishing works is being undertaken at the Croydon Station during day and intermittent night works. Night works are scheduled to be undertaken each night, between 1am   and 5am (approximately), from Tuesday 30 January to Saturday 3 February (finishing 5am Saturday 3 February) […]

UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD BETWEEN HAWKER STREET AND PORT ROAD, WITH TEMPORARY CLOSURE OF SOUTH ROAD – THURSDAY 18-MONDAY 22 JANUARY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement and asphalt works in the southbound lanes of South Road between Hawker Street and Port Road. To minimise disturbance to peak hour traffic, the works will be undertaken at the following times, weather permitting: Hawker Street to […]

UPCOMING NIGHT WORKS ON TORRENS ROAD BETWEEN DAYS ROAD AND WRIGHT STREET – 21-24 JANUARY 2018

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a new water main on Torrens Road between Days Road and Wright Street, and on South Road between Bishop Street and Torrens Road. To minimise disturbance to peak hour traffic, and weather permitting, these works will be […]

UPDATE: RAIL WORKS BETWEEN QUEEN STREET/CROYDON STATION AND WEST STREET

As part of the Torrens Road to River Torrens Project, a range of works is being undertaken in the rail corridor between Queen Street and West Street to upgrade the level crossings and the Croydon Station. Train services on the Outer Harbor line returned from the first service on 15 January 2018, however, finishing works […]

SUPPORT YOUR LOCAL BUSINESS DURING CONSTRUCTION OF THE TORRENS ROAD TO RIVER TORRENS PROJECT

CLICK ON THE BELOW LINK TO VIEW THE LOCAL BUSINESS ADVERTISEMENTS AND OFFERS Supporting local business  

Supporting local businesses

The T2T Project and the Torrens Rail Junction Project, together with the Australian and South Australian Governments, are supporting a Local Business Promotion in the Portside/Westside Weekly Messenger newspapers, published on Wednesday 13 December 2017. A number of businesses located in or adjacent to the Project areas have placed advertisements. This is an opportunity to […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH TORRENS ROAD, RIDLEYTON – 3-5 DECEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking common services trench works in the southbound lanes of South Road, through the intersection with Torrens Road. To minimise disturbance to peak hour traffic and weather permitting, the works will take place between 7pm and 6am on Sunday 3 […]

UPDATE: NIGHT AND DAY WORKS IN THE RAIL CORRIDOR AT QUEEN STREET AND CROYDON STATION- 27 NOVEMBER – 21 DECEMBER 2017

As part of the Torrens Rail to River Torrens Project, works are continuing in the rail corridor, between Queen Street and Croydon Station, Croydon, weather permitting. In order to complete these works as soon as possible, intermittent day and night works will be required from 7pm Monday 27 November to 5pm Thursday 21 December. Key activities Backfilling L-walls […]

UPCOMING WEEKEND AND NIGHT WORKS ON SOUTH ROAD BETWEEN TORRENS ROAD AND FORSTER STREET, RIDLEYTON – 24-28 NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement works in the southbound lanes of South Road between Torrens Road and Forster Street, Ridleyton. To minimise disturbance to peak hour traffic, the works will be undertaken from 8pm Friday 24 November to 6am Monday 27 November […]

UPCOMING NIGHT WORKS ON SOUTH ROAD BETWEEN PORT ROAD AND GRANGE ROAD / MANTON STREET- 15 – 16 NOVEMBER AND 16 – 17 NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing inclinometers on South Road between Port Road and Grange Road / Manton Street. To minimise disturbance to peak hour traffic, and weather permitting, the works will be carried out during the following times: From 7pm Wednesday 15 November to […]

UPCOMING NIGHT AND WEEKEND WORKS ON SOUTH ROAD BETWEEN TORRENS ROAD AND HAWKER STREET, RIDLEYTON WITH TEMPORARY CLOSURE OF SOUTH ROAD- FRIDAY 10 NOVEMBER – MONDAY 13 NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement and asphalt works in the southbound lanes of South Road between Torrens Road and Hawker Street, Ridleyton. To minimise disturbance to peak hour traffic, the works will be undertaken from 8pm Friday 10 November to 6am Monday […]

UPCOMING NIGHT WORKS ON PORT ROAD, CROYDON – 13 – 17 NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking service relocation works on Port Road, between South Road and Queen Street, Croydon and installing gantries in the median on Port Road (outbound) near Coglin Street, Hindmarsh and inbound near Queen Street, Croydon. On completion of the project, the […]

UPCOMING NIGHT WORKS ON SOUTH ROAD- 30 OCTOBER – 3 NOVEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking common services trench works in the southbound lanes of South Road between Torrens Road and Hawker Street. To minimise disturbance to peak hour traffic, and weather permitting, the works will take place between 7pm and 6am from Monday 30 […]

UPDATE: NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH PYM STREET, CROYDON PARK – 15 OCTOBER – 16 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a new water main in the northbound lanes of South Road across the intersection with Pym Street, and on Pym Street, west of the intersection. To minimise disturbance to peak hour traffic and safely facilitate these works, […]

UPCOMING NIGHT WORKS ON SOUTH ROAD- 6 – 7 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install infrastructure for the Intelligent Transport Systems (ITS) on both sides of South Road between Overland Road and Lamont Street. To minimise disturbance to peak hour traffic, and weather permitting, the works will be carried out intermittently each […]

UPCOMING NIGHT WORKS ON SOUTH ROAD- 6 – 7 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install infrastructure for the Intelligent Transport Systems (ITS) on both sides of South Road between Gawler Avenue and Susan Street. To minimise disturbance to peak hour traffic, and weather permitting, the works will be carried out intermittently each […]

RAIL WORKS UPDATE- 6 OCTOBER 2017

During the works to upgrade the Queen Street level crossing and the Croydon Station, erection of fencing around the works site will commence on Thursday 6 October 2017. In addition to this activity, increased truck movements into and out of the rail corridor will be observed from early next week. Trucks will enter the rail […]

UPCOMING NIGHT WORKS AT THE SOUTH ROAD INTERSECTION WITH HAWKER STREET – 10-13 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing inclinometers on South Road near the intersection with Hawker Street, and on South Road near the Croydon Shopping Centre. To minimise disturbance to peak hour traffic, and weather permitting, the works will be carried out each night between 7pm […]

UPCOMING NIGHT WORKS ON THE PEDESTRIAN CROSSING OF SOUTH ROAD ADJACENT PAGET STREET AND CEDAR AVENUE – 9-12 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing inclinometers on both sides of the pedestrian bridge over South Road adjacent Paget Street and Cedar Avenue. To minimise disturbance to peak hour traffic, and weather permitting, the works will be carried out each night between 7pm and 6am […]

UPCOMING NIGHT AND WEEKEND WORKS SOUTH ROAD INTERSECTION WITH PORT ROAD WITH TEMPORARY CLOSURES OF PORT ROAD AND SOUTH ROAD – 29 SEPTEMBER – 3 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance is undertaking pavement and asphalt reinstatement works at the South Road intersection with Port Road. To minimise disruption to peak hour traffic, these works will be undertaken from 8pm Friday 29 September to 6am Tuesday 3 October 2017, weather permitting. Depending on […]

UPCOMING WORKS ON SOUTH ROAD BETWEEN DAY TERRACE AND TORRENS ROAD – 3-16 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of activities on South Road, between Day Terrace and Torrens Road. The works will be undertaken intermittently between 7pm and 6am from Tuesday 3 October to Monday 16 October 2017 (finishing 6am Monday 16 October). Key activities […]

UPCOMING CLOSURE OF PEDESTRIAN CROSSING OF SOUTH ROAD ADJACENT PAGET STREET AND CEDAR AVENUE INCLUDING NIGHT AND WEEKEND WORKS ON SOUTH ROAD – 29 SEPTEMBER – 7 OCTOBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing the Cedar Avenue pedestrian bridge across South Road, between Paget Street and Cedar Avenue. To safely undertake these works the pedestrian crossing will be closed from 7pm Monday 2 October to 7am Saturday 7 October 2017. To minimise disturbance […]

UPDATE: UPCOMING NIGHT AND DAY WORKS IN THE RAIL CORRIDOR BETWEEN CHIEF STREET AND COGLIN STREET – 25 SEPTEMBER – TO MID DECEMBER 2018

Further to our notice of 20 September 2017, the T2T Alliance will be undertaking a range of works in the rail corridor, between Chief Street and Coglin Street, Brompton from 6am Monday 25 September to 13 December 2017, weather permitting. Residents and business proprietors close to the rail corridor can expect to see and hear […]

UPDATE: TEMPORARY ROAD CLOSURE – ORSMOND STREET AND SOUTH ROAD, HINDMARSH UNTIL 25 SEPTEMBER 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing a range of activities in the southbound lanes of South Road between Port Road and Manton Street, Hindmarsh. To safely undertake these works the Orsmond Street junction with South Road will continue to be temporarily closed until 6am Monday […]

UPCOMING EXCAVATION OF THE LOWERED MOTORWAY, SOUTH ROAD -UNDER PORT ROAD

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing excavation of the lowered motorway under Port Road. The works will be undertaken each night between 7pm and 6am from: Wednesday 30 August to Saturday 2 September 2017 (finishing 6am Saturday 2 September) Monday 4 September to Friday 8 […]

UPDATE: TEMPORARY CLOSURE OF FOOTPATH ON THE WESTERN SIDE OF SOUTH ROAD BETWEEN PYM STREET AND ROYCE AVENUE, CROYDON PARK- FROM 21 AUGUST 2017

Due to the recent wet weather these works did not proceed as previously advised. As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new kerbing and footpaths, stormwater infrastructure and pavements in the southbound lanes of South Road between Pym Street and Royce Avenue. To safely facilitate these […]

UPCOMING NIGHT AND WEEKEND WORKS ON PORT ROAD BETWEEN SOUTH ROAD AND QUEEN STREET – 18/08/2017 – 21/08/2017

As previously advised, the T2T Alliance is undertaking kerbing, pavement and asphalt reinstatement works on the northern side of Port Road between South Road and Queen Street. To minimise disruption to peak hour traffic, the works will now undertaken from 7pm Friday 18 August to 6am Monday 21 August 2017, weather permitting. Intermittent night works […]

NIGHT AND WEEKEND WORKS IN THE RAIL CORRIDOR BETWEEN QUEEN STREET AND CHIEF STREET- 18/8/2017 – 21/8/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking works along the rail corridor between Queen Street, Croydon and Chief Street, Brompton from 7pm Friday 18 August to 6am Monday 21 August 2017, weather permitting. Works within the rail corridor will be undertaken during the temporary closure of […]

CONFIRMED – UPCOMING NIGHT AND WEEKEND WORKS ON GRANGE ROAD BETWEEN SOUTH ROAD AND BERTIE STREET, WEST HINDMARSH- 11/8/2017 – 14/8/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking major pavement and asphalt reinstatement works at the South Road intersection with Grange Road and Manton Street, and on Grange Road and Manton Street adjacent to South Road. To minimise disruptions to peak hour traffic, the works will be […]

UPDATE: TEMPORARY CLOSURE OF FOOTPATH ON THE WESTERN SIDE OF SOUTH ROAD BETWEEN GRANGE ROAD AND PORT ROAD, WEST HINDMARSH – UNTIL 26/08/2017

UPDATE: TEMPORARY CLOSURE OF FOOTPATH ON THE WESTERN SIDE OF SOUTH ROAD BETWEEN GRANGE ROAD AND PORT ROAD, WEST HINDMARSH Due to recent weather conditions, these works could not be completed as previously advised. As part of the Torrens Road to River Torrens Project, the T2T Alliance is installing an Intelligent Transport System (ITS), new […]

UPDATE: TEMPORARY ROAD CLOSURES: BISHOP STREET AND TAIT STREET, RENOWN PARK

As part of the Torrens Road to River Torrens Project, the T2T Alliance is installing new stormwater infrastructure along the southbound lanes of South Road between Sunbeam Road and Tait Street, Renown Park. To safely facilitate these works, the following temporary road closures will be in place: Bishop Street: o  To remain temporarily closed at […]

UPCOMING EXCAVATION OF THE LOWERED MOTORWAY, SOUTH ROAD – 31/7/2017 – 5/8/2017 AND 7/8/2017 – 12/8/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing excavation of the lowered motorway, between Port Road and Cedar Avenue. The works will be undertaken between 7pm and 6am from: Monday 31 July to Saturday 5 August 2017 (finishing 6am Saturday 5 August) Monday 7 August to Saturday […]

UPCOMING PILING WORKS AT TAYLOR BRIDGE – 14/07/2017 – 28/07/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking intermittent piling works at Taylor Bridge between 7am and 5pm, Monday to Saturday, from Friday 14 July to Friday 28 July 2017. Key activities Driven pile works to install four 1000mm diameter steel tube piles A hydrohammer and 350t […]

UPCOMING WEEKEND AND NIGHT WORKS ON PORT ROAD, CROYDON – 7/7/2017 – 10/7/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing kerbing on the northern side of Port Road (from 429 to 431 Port Road, Croydon). To minimise disturbance to peak hour traffic, intermittent day and night works will be undertaken from 7pm Friday 7 July to 6am Monday 10 […]

ASPHALTING WORKS AT THE EASTERN END OF DAY TERRACE, CROYDON – 3/7/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking asphalting works within the fenced T2T Project area at the eastern end of Day Terrace, Croydon from 7am to 4pm Monday 3 July 2017, weather permitting.. During these works, trucks will be accessing the site via Queen Street and […]

UPCOMING NIGHT AND WEEKEND WORKS: TRAFFIC SWITCH ON SOUTH ROAD BETWEEN HINDMARSH AVENUE AND GAWLER AVENUE, WEST HINDMARSH – 02/07/2017 – 04/07/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of intermittent day and night works in the southbound lanes of South Road, between Manton Street and Hindmarsh Avenue, from July to October 2017. Further details will be provided as the works progress. The works will include: […]

UPCOMING NIGHT AND WEEKEND WORKS ON CORNER OF SOUTH ROAD AND GRANGE ROAD, WEST HINDMARSH – 21/6/2017 and 23/6/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking driveway and footpath works on the corners of South Road and Grange Road, and in the northbound lanes of South Road, approximately 50 metres, either side of Grange Road. To minimise disruption to peak hour traffic, and weather permitting, […]

TEMPORARY CLOSURE OF LINEAR PARK TRAIL, BETWEEN MCDONNELL AVENUE AND SOUTH ROAD, AND THE WESTERN FOOTPATH ON SOUTH ROAD, ACROSS TAYLOR BRIDGE – 27/5/2017 – LATE 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be widening Taylor Bridge (bridge across the River Torrens) from 27 May 2017 until late 2017. To facilitate these works: The Linear Park Trail will be temporarily closed between McDonnell Avenue and South Road. Signage will be erected in strategic locations […]

UPDATE: WORKS POSTPONED! UPCOMING NIGHT AND WEEKEND WORKS ON PORT ROAD BETWEEN ALBERMARLE STREET AND LINDEN STREET – 26/5/2017 – 29/5/2017

Please be advised that due to forecasted rainfall, the works scheduled to take place this weekend on Port Road, between Albemarle and Linden Street have been postpone. These works will rescheduled from 7pm Friday 2 June to 6am Monday 5 June 2017 (see attached notice). As previously advised, the T2T Alliance will be undertaking pavement […]

UPCOMING NIGHT AND WEEKEND WORKS: SOUTH ROAD INTERSECTION WITH GRANGE ROAD/MANTON STREET- 17 – 20 MARCH 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking works to implement changes to traffic arrangements at the South Road intersection with Grange Road/Manton Street. These changes include the opening of right turn movements from South Road northbound into Manton Street. Weather permitting, the works will be undertaken […]

UPCOMING NIGHT WORKS, SOUTH ROAD JUNCTION WITH ROYCE AVENUE – 16/02/2017 – 17/02/2017

As part of the Torrens Road to River Torrens Project, Telstra will be connecting the bore pipe to the manhole at the South Road junction with Royce Avenue. These works will take place from 7pm Thursday 16 February to 1am Friday 17 February 2017. Equipment A vacuum truck, compaction equipment, trucks, and light vehicles will […]

UPCOMING NIGHT WORKS AT TAYLORS BRIDGE FOR VEGETATION REMOVAL – 2/2/17

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be removing vegetation in preparation for the widening of Taylors Bridge (bridge over the River Torrens). To minimise disturbance to peak hour traffic and local residents, the works will take place between 1pm and 9pm on Thursday 2 February 2017. A […]

UPCOMING NIGHT AND WEEKEND WORKS: INSTALLATION OF TRAFFIC SIGNAL CONDUITS ACROSS SOUTH ROAD NEAR THE PORT ROAD INTERSECTION -3/2/17 – 6/2/17

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing traffic signal conduits in the south bound lanes of South Road, just north of the intersection with Port Road. To minimise disturbance to peak hour traffic, the works will take place from 7pm Friday 3 February to 6am Monday […]

UPCOMING WORKS AT TAYLORS BRIDGE (BRIDGE OVER THE RIVER TORRENS)

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be widening the western side of Taylors Bridge. The works will start in February 2017 and take approximately 9 months to complete. To minimise disturbance to residents, the works will predominately be undertaken between the hours of 7am and 7pm, six […]

UPCOMING NIGHT WORKS ON SOUTH ROAD, RIDLEYTON – 16 -20 JANUARY 2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing new stormwater infrastructure on South Road, between Monmouth Street and Hythe Street. To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am from Monday 16 January to Friday 20 January 2017 (finishing 6am […]

Construction of the of the Outer Harbor rail overpass

Sunday 8 January marked another significant milestone for the Project when the first overpass segment for the Outer Harbor rail overpass was lifted into place.  We’ve posted a selection of photos here and a video here. The third segment was installed on Thursday 12 January 2017. Stay tuned for more photos and videos soon! Lifting […]

UPCOMING NIGHT WORKS: ASPHALTING WORKS ON PORT ROAD – 16/1/17 – 17/1/17

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be reinstating asphalt in the west bound and city bound lanes of Port Road, near Queen Street. To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am on Monday 16 January and Tuesday 17 January […]

UPCOMING MAJOR WORKS FOR CONSTRUCTION OF THE OUTER HARBOR RAIL OVERPASS – 02/01/2017 – 23/01/2017

As part of the Torrens Road to River Torrens Project, the T2T Alliance is undertaking major works in the Outer Harbor and Grange rail corridor, between Queen Street and Coglin Street, from 1am Monday 2 January 2017 to 6am Monday 23 January 2017. Works will be continuous, 24 hours per day to construct the Outer […]

Christmas / New Year Holiday Arrangements

The T2T Alliance will be taking a break from Friday 23 December until Wednesday 4 January 2017. During this period there will be no traffic restriction with only minor site specific construction activities taking place. Stock piles will be treated with a dust suppressant and watering carts will be in operation as required during the […]

UPCOMING DAY WORKS, SEWER MAIN WORKS: INTERSECTION OF DAYS ROAD WITH LAMONT STREET, CROYDON PARK- 19/12/2016 – 21/12/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install a new sewer main along Lamont Street close to the intersection with Days Road. The works will take place each day between 7am and 6pm from Monday 19 December to Wednesday 21 December 2016. The intersection of […]

UPCOMING NIGHT AND WEEKEND WORKS: TRAFFIC SWITCH TO THE NEW NORTHBOUND SURFACE ROAD AND INSTALLATION OF TEMPORARY U-TURNS ON SOUTH ROAD NEAR TORRENS ROAD- 7pm Friday 16 December to 6am Monday 19 December 2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be switching traffic to the new north bound surface road on South Road, between Torrens Road and Tait Street. In addition, temporary signalised u-turns will be installed on South Road near Tait Street and at Dartmouth Street. These works will take […]

UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS ON PYM STREET – between 7pm and 6am on Wednesday 14 December and Thursday 15 December 2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking service depthing and Telstra relocation works on Pym Street between South Road and Austin Street. To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am on Wednesday 14 December and Thursday 15 December […]

UPCOMING NIGHT WORKS AND TEMPORARY ROAD CLOSURE: DARTMOUTH STREET JUNCTION WITH SOUTH ROAD, WEST CROYDON

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be implementing temporary traffic arrangements at South Road intersection with Torrens Road to allow for construction of the new Torrens Road bridge and lowered motorway. Please refer to the  Temporary Traffic Arrangements at South Road Intersection with Torrens Road from Monday […]

UPCOMING NIGHT WORKS ON PYM STREET NEAR THE SOUTH ROAD INTERSECTION – 14/12/2016 – 15/12/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking service depthing to confirm the location of services on Pym Street on the western side of the South Road intersection. To minimise disturbance to traffic these works will be undertaken between 7pm and 6am on Wednesday 14 December and […]

UPCOMING WORKS: OVERLAND ROAD AT SOUTH ROAD (WESTERN SIDE), CROYDON PARK- from 18/11/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing construction works for the new north bound surface road and commencing installation of concrete noise walls at the South Road intersection with Overland Road. To complete these works, Overland Road will be closed at South Road from 5am Friday […]

Temporary traffic arrangements at South Road intersection with Grange Road/Manton Street- 21 November 2016

Grange Road/Manton Street and South Road traffic switch fact sheet November 201

TEMPORARY ROAD CLOSURE EXTENDED: CORNER OF THOMAS STREET AND HURTLE STREET, CROYDON- 4 NOVEMBER 2016

Due to the weather and technical difficulties, the pavement and asphalting works at the corner of Thomas Street and Hurtle Street will not be completed until Friday 4 November 2016. As a result of these works, the corner of Thomas Street and Hurtle Street will remain temporarily closed until 5pm Friday 4 November 2016. Key […]

UPCOMING WEEKEND AND NIGHT WORKS: CONTINUATION OF TRAFFIC SIGNAL AND STREET LIGHTING WORKS

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be continuing to install new traffic signals and street lighting at the South Road intersection with Grange Road / Manton Street. To minimise disturbance to peak hour traffic, the works will take place from: 7pm Thursday 27 October to 6am Friday […]

TEMPORARY FOOTPATH CLOSURE ON SOUTH ROAD

As part of the Torrens Road to River Torrens Project, the T2T Alliance has closing the footpath on the western side of South Road between Torrens Road and Overland Road. The footpath is closed to construct the new north bound surface road on South Road. Signage is in place to notify the public of the […]

UPCOMING NIGHT WORKS: SEWER MAIN WORKS ON SOUTH ROAD, HINDMARSH – 17 & 18 OCTOBER 2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be carrying out maintenance work on a sewer main in the south bound lanes of South Road, opposite Gawler Avenue, West Hindmarsh. To minimise disturbance to peak hour traffic, the works will take place between 7pm Monday 17 October and 3am […]

UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD- 25/9/2016 – 29/9/2016

The T2T Alliance will be continuing construction of a Common Services Trench within the eastern footpath of South Road, between Susan Street and Adam Street. To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am from Sunday 25 September to Thursday 29 September 2016 (finishing 6am Friday 30 September […]

UPDATE: TEMPORARY LOCAL ROAD CLOSURES BETWEEN PAGET STREET AND FORSTER STREET AT SOUTH ROAD- 21/9/2016 – 27/9/2016

The T2T Alliance is continuing with the installation of a Common Services Trench within the eastern footpath of South Road between Paget Street and Forster Street. To facilitate these works the Monmouth Street at South Road will be temporarily closed from 7pm Wednesday 21 September to 6am Tuesday 27 September 2016, subject to weather conditions. […]

TEMPORARY ROAD CLOSURES: MONMOUTH AND FORSTER STREETS AT SOUTH ROAD, RIDLEYTON- 13/9/2016 – 16/9/2016

The T2T Alliance will be installing a Common Services Trench within the eastern footpath of South Road between Torrens Road and Forster Street. To facilitate these works, Monmouth Street and Forster Street will be temporarily closed at   South Road from 7pm Tuesday 13 September to 6am Friday 16 September 2016. Paget Street and Hythe Street […]

UPDATED TIMINGS – UPCOMING NIGHT AND WEEKEND WORKS: SOUTH ROAD INTERSECTION WITH GRANGE ROAD/MANTON STREET – 7PM FRIDAY 9 SEPTEMBER – 6AM MONDAY 12 SEPTEMBER 2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be installing bridge beams at the South Road intersection with Grange Road/Manton Street (at the temporary signalised roundabout). When: The works will be undertaken from 7pm Friday 9 September – 6am Monday 12 September 2016. During the works, major traffic restrictions […]

UPCOMING NIGHT WORKS IN THE OUTER HARBOR RAIL CORRIDOR

The T2T Alliance will be relocating the piling rig and undertaking piling works for the Outer Harbor rail overpass. The piling rig will be relocated within the rail corridor on the north west corner of South Road. To minimise disturbance to train commuters these works will be undertaken between: 11:30pm Wednesday 31 August to 7am […]

UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD- 28/8/2016 – 8/9/2016

Over the next two weeks, the T2T Alliance will be continuing construction of a Common Services Trench within the eastern footpath of South Road, between Susan Street and Hindmarsh Avenue. To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am from Sunday 28 August to Thursday 8 September 2016 […]

UPCOMING NIGHT WORKS ON PORT ROAD BETWEEN QUEEN STREET AND KING STREET- 28/8/2016

The T2T Alliance will be removing traffic barriers in the Port Road median between Queen Street and King Street. To minimise disturbance to traffic, the works will be undertaken between 7pm Sunday 28 August and 6am Monday 29 August 2016.    Traffic Management Port Road will be reduced to one lane for westbound traffic between […]

UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD – 21/8/16 – 25/8/16

The T2T Alliance will be continuing construction of a Common Services Trench within the eastern footpath of South Road, between Susan Street and Hindmarsh Avenue. To minimise disturbance to peak hour traffic, the works will take place each night between 7pm and 6am from Sunday 21 August to Thursday 25 August 2016 (finishing 6am Friday […]

UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD – 21/8/16 – 25/8/16

The T2T Alliance will be continuing construction of a Common Services Trench within the eastern footpath of South Road, between Torrens Road and Forster Street. Multiple crews will be working across various sites within the area to complete the works. To minimise disturbance to peak hour traffic, the works will take place each night between […]

UPCOMING NIGHT AND WEEKEND WORKS AT THE SOUTH ROAD INTERSECTION WITH GRANGE ROAD AND MANTON STREET – AUGUST – OCTOBER 2016

From August to October 2016 there will be an ongoing program of activities associated with service relocations and bridge preparation works at the South Road intersection with Grange Road and Manton Street. These works will be undertaken during nights and on weekends to avoid disruptions to peak hour traffic. The range of key activities that […]

CLOSURE OF WILLIAM STREET AT SOUTH ROAD, CROYDON – 9/8/2016 – 22/8/2016

The T2T Alliance is currently undertaking an intensive program of works to prepare for the upcoming traffic switch to the new northbound surface road on South Road between Robert Street and Torrens Road. As a result of these works, William Street will be permanently closed at South Road from 7pm Tuesday 9 August 2016 as […]

Construction Newsletter July 2016

The 3rd edition of Construction Newsletter is now available. To view the Construction Newsletter please click here. The Outer Harbor rail overpass construction animation, as mentioned in the Construction Newsletter, will be added to the 3D animation page and the gallery soon.

UPCOMING NIGHT WORKS AT THE SOUTH ROAD AND TORRENS ROAD INTERSECTION, RENOWN PARK – 19/7/2016 – 20/7/2016

 The T2T Alliance will be undertaking service depthing to confirm the location of services at the South Road and Torrens Road intersection, Renown Park. To minimise disturbance to traffic these works will be undertaken from 7pm to 6am on Tuesday 19 July and Wednesday 20 July 2016 (finishing 6am Thursday 21 July 2016). Traffic Management […]

UPDATE: UPCOMING NIGHT AND WEEKEND WORKS FOR WORKS ON TORRENS ROAD, CROYDON PARK

Further to our notice dated 12 July 2016, some of the stormwater works on Torrens Road referred to in that notice have been re-scheduled. Below is a list of weekend works that will now occur on Torrens Road between Friday 15 July and Sunday 24 July 2016. Preparation works for installation of the storm water […]

UPCOMING DAY AND WEEKEND WORKS ON HENRY STREET, CROYDON – 15 – 16 July & 18 – 19 July 2016

The T2T Alliance will be installing a new gas main in Henry Street, between South Road and Elizabeth Street, Croydon. To minimise disturbance to residents, the works will be undertaken each day between 7am and 5pm on Friday 15 July, Saturday 16 July, Monday 18 July and Tuesday 19 July 2016.  No works will occur […]

UPCOMING NIGHT AND WEEKEND WORKS: SERVICE RELOCATION WORKS ON SOUTH ROAD, JUST SOUTH OF HURTLE STREET, CROYDON – 15/7/2016 – 18/7/2016

The T2T Alliance will be installing a stormwater junction box in the kerbside northbound lane of South Road, near Hurtle Street, Croydon. To minimise disturbance to traffic, the works will be undertaken from 7pm Friday 15 July to 6am Monday 18 July 2016, weather permitting. Key activities Pavement cutting and excavation. Installation of a junction […]

UPCOMING NIGHT AND WEEKEND WORKS: SEWER MAIN WORKS ON WILLIAM STREET, CROYDON- 15/7/2016 – 17/7/2016

The T2T Alliance will be undertaking sewer main testing and minor repair works on William Street between Elizabeth Street and South Road, Croydon from 7pm Friday 15 July to 9am Sunday 17 July 2016. Works may be completed earlier than scheduled, subject to weather conditions. These are essential works that must be undertaken prior to […]

UPCOMING NIGHT WORKS: SERVICE RELOCATION WORKS

The T2T Alliance will be directional drilling communication conduits underneath South Road, from Ridley Street, Hindmarsh to Princes Street, Croydon. To minimise disturbance to peak hour traffic, the works will take place between 7pm and 6am on Monday 16 May and Tuesday 17 May 2016 (finishing 6am Wednesday 18 May 2016).   Traffic Management Traffic […]

TEMPORARY TRAFFIC ARRANGEMENTS FOR THE SOUTH ROAD INTERSECTION WITH PORT ROAD DURING STAGE 3 TRAFFIC SWITCH WORKS

As part of the Torrens Road to River Torrens Project, a range of activities is being undertaken for Stage 3 traffic switch to allow construction of a new bridge at the South Road intersection with Port Road.  Works will take place from 7pm Friday 6 May 2016 until 6am Monday 9 May 2016, when the […]

UPDATE: UPCOMING TRENCHING WORKS ON HURTLE STREET FOR THE RELOCATION OF SERVICES

The T2T Alliance will be trenching along Hurtle Street, Croydon between Thomas Street and South Road to relocate services in the area. To minimise disturbance to the local community, the works will take place each day between 7am and 7pm from Wednesday 4 May to Friday 6 May 2016. An excavator, trucks for carting materials, […]

CHANGES TO TRAFFIC ARRANGEMENTS ON PORT ROAD – TRAFFIC SWITCHES STAGES 2 & 3

Following the successful completion of the Stage 1 traffic switch on South Road, the next two traffic switches on Port Road are scheduled to take place on:  the night of Wednesday 27 April 2016; and the weekend of 7 – 8 May 2016. For more details of the traffic arrangements on Port Road, once the […]

Grange Road Traffic Switch April 11 2016 – Time lapse footage

Time lapse footage was taken of the South Road intersection with Grange Road/Manton Street traffic switch works from April 8 and 11 2016. This footage shows the large amount of work that occurred over the weekend to make the traffic switch possible. To view this footage please click here.  

UPCOMING TRAFFIC SWITCHES – SOUTH ROAD INTERSECTION WITH GRANGE ROAD/MANTON STREET AND PORT ROAD APRIL 2016

In April 2016, road works will be undertaken at the South Road intersection with Grange Road/Manton Street, and at the South Road intersection with Port Road, to switch traffic onto the new northbound surface road alignment between Hindmarsh Avenue, West Hindmarsh and Euston Terrace, Croydon. The traffic will be redirected to allow for the construction […]

UPCOMING WEEKEND WORKS:  Outer Harbor rail line works – Croydon – 09/04/16 – 11/04/16

As part of the Torrens Road to River Torrens Project, there will be a temporary partial closure of the Outer Harbor rail line between Adelaide Station and Woodville Station from Saturday 9 April 2016 until the first service Monday 11 April 2016.  Works will occur between 2am Saturday 9 April 2016 and 4am Monday 11 […]

UPCOMING NIGHT AND WEEKEND WORKS – SOUTH ROAD INTERSECTION WITH GRANGE ROAD AND MANTON STREET, WEST HINDMARSH – 04/04/16 – 07/04/16

As part of Torrens Road to River Torrens Project, an ongoing program of activities in preparation for the traffic switch onto the new, northbound road alignment between Hindmarsh Avenue, West Hindmarsh and Grange Road, West Hindmarsh will take place from Monday 4 April to Thursday 7 April 2016 Hours of work: between 7pm and 6am […]

UPDATE: UPCOMING NIGHT AND DAY WORKS: SERVICE RELOCATION WORKS – 30/03/16 – 5/04/16

The T2T Alliance will continue the directional drilling underneath Torrens Road, from Scotia Street, Croydon (adjacent to South Road) to the north-west corner of South Road and Torrens Road intersection, Renown Park. These works form part of the electrical service relocation works. To minimise disturbance to peak hour traffic, most of the works will take […]

NO MAJOR WORKS PLANNED OVER THE EASTER LONG WEEKEND

The T2T alliance would like to advise that there will be no major works planned for the Easter long weekend 2016. While some minor activity may still be noticeable on the site, there will be no night works or site specific works from the evening of Thursday 24 March until 7pm Monday 28 March 2016. […]

PYM STREET DESIGN OPTIONS – HAVE YOUR SAY

The T2T Alliance is investigating the design solution to provide turning movements at Pym Street. The early concept design for the Pym Street intersection was released in February 2016. Based on additional detailed traffic modelling, the T2T Alliance is now seeking community feedback on two alternative design options for Pym Street, which are considered to offer improvements to […]

UPCOMING NIGHT WORKS FOR SERVICE DEPTHING ON SOUTH ROAD, RIDLEYTON – 15/03/2016 – 20/03/2016

The T2T Alliance will be service depthing to identify the location of services on South Road, Ridleyton between Forster Street and Paget Street. To minimise disturbance to peak hour traffic, the works will take place each night from 7pm to 6am from Tuesday 15 March, 2016 to Sunday 20 March, 2016. Works will progressively move […]

UPCOMING NIGHT AND WEEKEND WORKS AT THE GRANGE ROAD / MANTON STREET & SOUTH ROAD INTERSECTION

As part of the Torrens Road to River Torrens Project, water main and traffic signalling conduit installation works will be undertaken at times to minimise disruption to peak hour traffic. These works will take place from: 7pm Thursday 10 March, 2016 to 6am Friday 11 March, 2016 10pm Friday 11 March, 2016 to 6am Tuesday, […]

SCOTIA STREET – PLANNED WATER OUTAGE CANCELLED 8/03/2016

Due to a conflict with existing services in the area, the planned water outage will not take place on Tuesday 8 March 2016. A new notice will be issued once the conflict has been resolved. Sorry for any inconvenience this may have caused. For further information about these works, including the latest traffic arrangements, please […]

UPCOMING WEEKEND AND NIGHT WORKS: WATER MAIN INSTALLATION – GRANGE ROAD, WEST HINDMARSH AND MANTON STREET, HINDMARSH – 26/02/2016 – 29/02/2016

The T2T Alliance is undertaking a range of activities to install a new water main along the northern side of Grange Road and Manton Street between Bertie Street, West Hindmarsh and Bacon Street, Hindmarsh. To minimise disruption to peak hour traffic, the work will be undertaken from 7pm Friday 26 February, 2016 to 6am Monday, […]

UPDATE: TEMPORARY CHANGE TO ACCESS ARRANGEMENTS INTO THE T2T STAFF CAR PARK – PRINCES STREET, CROYDON

As previously advised, the T2T Alliance has been trenching across Princes Street, Croydon (at the South Road end) in preparation for installation of the new sewer main. Works progress has been slower than anticipated, as other service relocation works have also been underway in the same area during the last month. Trenching works for the […]

UPCOMING NIGHT WORKS: WATER MAIN INSTALLATION – 22/02/2016 – 23/02/2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance is undertaking a range of activities to relocate services across McInnes Street, near South Road, Ridleyton. The activities include isolating and cutting the water main, followed by excavating and replacing the water main. To minimise disruption to peak hour traffic, night works […]

UPCOMING NIGHT AND WEEKEND WORKS: WATER MAIN INSTALLATION- 19/02/2016 – 22/02/2016

The T2T Alliance is undertaking a range of activities to install a new water main on Port Road, between Bertie Street and Linden Street, West Hindmarsh. Continuing on from last weekend’s works to install the water main, the T2T Alliance will now be connecting into existing services for the continuation of supply.  To minimise disruption […]

TORRENS ROAD TO RIVER TORRENS PROJECT CONSTRUCTION NEWSLETTER, EDITION 2 FEBRUARY 2016

UPDATE: The latest Torrens Road to River Torrens Project Construction Newsletter, Edition 2- February 2016 has been updated,  to correct a text error which incorrectly referred to McInnes Street, Ridleyton as being ‘left in /left out’. In the ‘Concept Design’ insert of the newsletter, it shows the correct access arrangements for McInnes Street  as being […]

UPCOMING DAY WORKS – VEGETATION REMOVAL AND PRUNING ON EUSTON TERRACE AND DAY TERRACE, CROYDON- 16/02/2016 – 19/02/2016

The T2T Alliance will be undertaking some tree removals and tree pruning in the rail corridor, adjacent to Day Terrace and Euston Terrace, Croydon between South Road and Queen Street from 16 to 19 February, 2016. These works include: Removal of two small self-seeded cedar trees towards the South Road end of Euston Terrace, to […]

UPCOMING NIGHT WORKS: SERVICE DEPTHING AND TRAFFIC BARRIER REMOVALS 17/02/2016

The T2T Alliance will be undertaking service depthing for electrical services on South Road, near Bond Street, West Hindmarsh. To minimise disturbance to peak hour traffic, the works will take place from 7pm to 12 midnight on Wednesday 17 February, 2016. To undertake these works, 3 traffic barriers will be temporarily removed while the service […]

UPDATE: TEMPORARY CLOSURE OF MCINNES STREET AT SOUTH ROAD- 28/03/2016

Further to our notice dated 15 January 2016 regarding the closure of McInnes Street from Wednesday 27 January to Saturday 20 February, 2016 for service relocation works and installation of a manhole across McInnes Street near South Road, we advise that this work will now continue through to 7am Monday 28 March, 2016. For further […]

UPCOMING NIGHT AND DAY WORKS: SERVICE RELOCATION WORKS 15/02/2016 – 26/02/2016

The T2T Alliance will be directional drilling  underneath Torrens Road, from  Scotia Street, Croydon (adjacent to South Road) to the north-west corner of the South Road and Torrens Road intersection, Renown Park. This forms part of the electrical service relocation  works. To minimise disturbance to peak hour traffic,  most of the works will take place […]

UPDATE: STORMWATER DRAINAGE WORKS ON PORT ROAD UNTIL 31/03/2016

Further to our notice dated 13 January 2016 regarding stormwater drainage works on Port Road, between Bourn Avenue and South Road, West Hindmarsh during January and February 2016, we advise that this work will now continue through to 31 March 2016. We thank you for your ongoing understanding while these important works are being undertaken. […]

Outer Harbor Greenway – Alternative route map

The Torrens Road to River Torrens Project when completed, will provide improved pedestrian and cycling facilities to the project area such as: an overpass of South Road for the Outer Harbor Greenway; a continuation of the Greenway along the rail corridor between South Road and Coglin Street; and a cyclist and pedestrian bridge across the […]

UPCOMING WORKS: PEDESTRIAN FOOTPATH TEMPORARILY CLOSED FROM HURTLE STREET TO SOUTH ROAD – 10/2/16

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be closing the footpath from Hurtle Street to South Road. The footpath will be temporarily closed from Wednesday 10 February 2016 for approximately two weeks . Pedestrian access to South Road will be available via Harriet Street. Temporary changes to pedestrian […]

UPCOMING NIGHT AND WEEKEND WORKS – RE-OPENING OF LANES ON PORT ROAD- 5/2/16 – 8/2/2016

Further to the notice dated 29 January, 2016 advising all traffic lanes on Port Road, between King Street, West Croydon and Anne, West Hindmarsh will re-open on Monday 8 February, we advise that works will occur this weekend in preparation for the lane re-opening. Works will start 7pm Friday 5 February, 2016 and be completed […]

UPCOMING NIGHT WORKS ON ROBERT STREET, CROYDON- 8/2/16 – 9/2/16

The T2T Alliance is currently completing trenching works on Robert Street and will be asphalting the services trench across Robert Street near the South Road end, on Monday 8 February 2016. Works will commence after 7pm and be completed by 11pm (approximately). Providing there are no unforeseen circumstances encountered during these works, Robert Street at […]

TEMPORARY ROAD CLOSURES: CROYDON AREA FOR RELOCATION OF SERVICES – 8/2/16 – 27/2/16

The T2T Alliance is working with Service Authorities to relocate a range of services in the area. As part of this ongoing program of works the following temporary local road closures will be put in place near South Road. Day Terrace Closed from 7pm Wednesday 17 February, 2016 Open from 7pm Saturday 27 February, 2016 […]

TRAFFIC LANES ON PORT ROAD TO RE-OPEN – 6AM MONDAY 8 FEBRUARY, 2016

The T2T Alliance has been installing a new water main and stormwater drainage pipes, as well as undertaking other service relocation works along Port Road between Anne Street, Hindmarsh and King Street, Croydon during December 2015 and January 2016. Service relocation works and other activities will continue on Port Road through February and March 2016. […]

TEMPORARY CLOSURE OF MEDIAN CROSSINGS ON PORT ROAD

As part of the Torrens Road to River Torrens Project, the T2T Alliance and SA Water are continuing the installation of new water mains in the Port Road median between Anne Street, Hindmarsh and King Street, Croydon. As part of these works, the following median crossings will be temporarily closed to trench across the medians: […]

STATE GOVERNMENT KEEPS BUILDING SOUTH AUSTRALIA IN 2016

Photo: (L – R) Kate Griffen, Andre Cronje, Hon Mr Stephen Mullighan and Malcolm McNeil. Construction will begin on almost $2.5 billion of major infrastructure projects in South Australia this year creating thousands of jobs. Click here to view the media release.

UPDATE- DELAY IN OPENING THE COGLIN STREET MEDIAN CROSSING

Please be advised that due to unforeseen circumstances that were encountered during water main relocation works last night, Coglin Street will not re-open this morning as previously advised. A team will be working tonight to complete works and the Coglin Street median crossing  is now re-scheduled to re-open by 6am Friday 22 January, 2016. We […]

INTERACTIVE CONSTRUCTION ZONE MAP AND TRAFFIC INFORMATION

With major construction works on the Torrens Road to River Torrens Project starting in January 2016 there is a large amount of information available to the public and key stakeholders about the project on this website.  In order to help make this information more easily available to the community, two new pages have been launched. […]

UPCOMING WORKS IN JANUARY 2016

As part of the Torrens Road to River Torrens Project, the T2T Alliance will be undertaking a range of works during January 2016 at various locations including: Port Road, between Anne Street, Hindmarsh and King Street, Croydon. South Road intersection with Port Road, Hindmarsh. South Road, between Paget Street, Ridleyton and Port Road, Hindmarsh. Grange […]

TORRENS ROAD TO RIVER TORRENS PROJECT SCOPE EXTENSION: Grade Separation of South Road and Torrens Road

SCOPE EXTENSION ANNOUNCEMENT 12 DECEMBER, 2015 For information on the scope extension including a drive through animation and artist impressions please visit: http://infrastructure.sa.gov.au/nsc/torrens_road_to_river_torrens_project/scope_extension To view the media release please click on the link below: 12 December 2015 -Another big win for motorists as T2T extended again TORRENS ROAD TO RIVER TORRENS PROJECT SCOPE EXTENSION CONCEPT DESIGN […]

STREET CORNER MEETING- WEST HINDMARSH

We will be holding two street corner meetings in November 2015, if you have any questions about the project please drop by. The meetings will be held between 5.30pm – 6.30pm, weather permitting, at the following locations: Tuesday 10 November, 2015 Langman Reserve Jervois Avenue / Hindmarsh Avenue, West Hindmarsh Thursday 12 November, 2015 Bond […]

HAWKER/HURTLE STREET INTERSECTION FINAL DESIGN

Following a review by the T2T Alliance and the Department of Planning, Transport and Infrastructure (DPTI) the design for the Hawker/Hurtle Street intersection has been finalised and endorsed by the City of Charles Sturt. The layout for the design is attached overleaf. The final design incorporates comments received from the Community Liaison Group, residents and […]

Community Information Day 15 August

A Community Information Day is being held on Saturday 15 August 2015 at the T2T Alliance site office on the corner of South Road and Ridley Street, Hindmarsh (limited car parking on Ridley Street.) Enjoy a FREE SAUSAGE SIZZLE cooked by the West Torrens Rotary Club (goods supplied by Croydon Foodland) Come along anytime between […]